Import text or CSV file 3.0
Summary
This operator allows to import data from a text file where values are separated by comma (comma separated values, CSV) or another symbol.
It can only be applied to an empty data node.
The text file has to be available in the Data Management on the TIS Server. Therefore, a file from a local storage has to be uploaded to the TIS Server. See Upload or download a data file to the TIS Server for how to do this.
Import via Parameters | As of version 5.8 import files can be defined via Parameters. |
Error Node | As of version 5.8 a specific error node can be defined. This way, error nodes can be displayed in TIS Board. The error node contains data rows that could not be properly interpreted. |
Example: Import text file of the type "Date/Time/Time"
Situation | The text file Import_1.txt is to be imported into a data node. |
Step 1 | Go to Homepage and choose the Data Management tab; upload file (Upload or download a data file to the TIS Server) |
Step 2 | Create an empty data node. To this node, add the operation "Import Text or CSV file 3.0". Click on the folder symbol next to "Name" and select the import file. Alternatively, files can be defined via parameters under "Path (manual):"
Then choose the following settings: Then click "Execute" to let TIS suggest the columns based on your suggestions. You will need to correct the suggested column "Bis" to Semantics: "Time (end)".
As of version 5.8 a specific error node can optionally be defined. That gives the possibility that error nodes can be displayed in TIS Board. Create an empty data node and choose the node as data node in the import operation. |
Result |
|
Further steps | The resulting table should be converted to date+time/date+time to allow operations such as Scaling 7.0 |
TIS Project |
Want to learn more?
Settings
Imports data from a text file.
Parameter
Examples
Example 2: Import file of type date+time/date+time
Situation | Read in the text file Import_2a.txt First, save the file on your PC and then import it into TIS (see TIS:Datenmanagement (link to old wiki)). Create an empty node in the TIS project and add operation "Import text or csv-file". |
Operation setting | Click on the folder symbol next to "Name" and select the import file. Alternatively, files can be defined via parameters under "Path (manual):" Then, chose the following settings: Click "Execute" to let TIS suggest the columns based on your suggestions. You will need to correct the suggested column "Bis" to Semantics: "Date+Time (end)". Please note: Click on the button "Edit" to change settings. Click on the button "Apply" to confirm changes. As of version 5.8 a specific error node can optionally be defined. That gives the possibility that error nodes can be displayed in [TIS]Board. Define an empty data node and choose the node as data node in the import operation. |
Result | |
TIS Project |
Example 3: Import file of type date+time/date+time with overlap to the next day
Situation | Read in the text file Datum;Von;Bis Please note: Times overlapping to the next day are indicated by different formats here: 25:00, 5:00+, and 6*00. This example will demonstrate how to read in each of these formats. |
Operation setting | One solution for this is to apply the Formula operator (row-by-row) (4.0) = Formeloperator to create new columns which calculate the correct date and time: Formulas are: 1. NextDay [Ja/Nein]: #Bis#.Substring(#Bis#.Length-1 > 0 ? #Bis#.Length - 1 : 0) == "+" || #Bis#.Contains("*") |
Result | |
TIS Project |
Troubleshooting
Problem | Frequent Cause | Solutions |
---|---|---|
Everything is suggested as Identifier although I wanted to read in Text. |
|
|
How can I make changes to the "Mapping" table? |
| |
"Execute" is suggesting only 1 column with all column titles in "Mapping" | Commong error: Wrong column separator has been chosen (e.g., semicolon instead of tabulator) | Check column separator, change it and click "execute" |
The operation does not read in the decimal points (or not in every column) |
|
|
24:00 is not imported correctly | 24:00 is no allowed format, because in most software systems it means that it is already the next day. | 1. Trick: Replacement of illegal values in combination with formula operator:
If the column that needs to be changed is named "Datum", then you can copy this formula: #Datum#.AddSeconds(#Datum#.Second == 59 && #Datum#.Minute ==59 && #Datum#.Hour==23 ? 1 : 0) |